Lambton Bridge
The project involved constructing a new 180-metre bridge over the Sauvage River in Lambton to replace the existing structure. The new bridge features two piers in the river, deep foundations, a steel superstructure, and a reinforced concrete deck. Once traffic was diverted to the new bridge, the old structure was dismantled to complete the infrastructure replacement.

Lambton Bridge

Building with 70 feet of water beneath your feet
Secteur — Travaux civils
Budget — 10m $ - 20m $
Échéancier — 44 semaines
Date de réalisation — 2024
Sector — Construction
Civil
Budget —
10M$ à 20M$
Timeline —
126 weeks
Completion date —
2021
The project involved constructing a new 180-metre bridge over the Sauvage River in Lambton to replace the existing structure. The new bridge features two piers in the river, deep foundations, a steel superstructure, and a reinforced concrete deck. Once traffic was diverted to the new bridge, the old structure was dismantled to complete the infrastructure replacement.
The challenge
Constructing the foundations directly in the river was one of the most complex phases of the project. The caisson piles had to be drilled from barges in nearly 70 feet of water, reaching depths of over 110 feet. The sheer size of the steel caissons and rebar cages, combined with the challenges of working on the water, required exceptionally precise coordination of all operations.
Our approach
To carry out this work, each sequence was planned based on the equipment, river conditions, and environmental constraints. Special attention was given to the management of sediment and drilling mud, as well as the handling of steel caissons and rebar cages. Once the foundations were completed, the steel structure was installed using the launching method, allowing construction to progress steadily over the river.
Results
The project replaced the existing infrastructure with a new, sustainable structure tailored to the needs of its users. Once traffic was diverted to the new bridge, the old structure was dismantled—including the removal of concrete from the riverbed—to complete the work while respecting the surrounding environment.